SATELLITE FIRE STATION OCCURRENCE REPORT v2

Shift Shift Cycle Date Emergency Drill
ALPHA SFS Night April 12, 2026 10 18

Shift Manning

Name Vehicle
SFM M Hafizudin Zainudin RIV3
FM Muhammad Yazid bin Abd Rahman RIV3
Khairul Najmi Bin Zainal ALP
Mohd Faidhi Bin Mohd Shamsudin DP
Mohd Hasif Bin Salami FT5
Mohd Hazeem Bin Abdul Halim MRV2
Mohd Jalludin Bin Jamil FT5
Mohd Ashraf Bin Malim Diman DP
Mohd Sharul Hisham Bin Kamaruddin WT
Muhamad Hafiz bin Baseri PM2
Mohamad Sufian Bin Mohd Lazi MRV2
Wan Amirul Syafiq bin Wan Azlan HZ2
Mohd Irwan Syah Bin Rohaizan HZ2
Rushairi Bin Arshad -

Staff On Leave

Name Leave Type

Occurrence Book Entry

Time Remarks
20:00

RO 32045 RUSHAIRI BIN ASHAD TERIMA TUGAS MENJAGA OCC DALAM BAIK.

20:10

ANGGOTA BERTUGAS MEMBUAT UJIAN RADIO KEPADA OCC TERIMA TERANG DAN JELAS.

20:13

ANGGOTA BERTUGAS MEMBUAT PEMERIKSAAN JENTERA DAN PERALATAN OPERASI MEMASTIKAN DALAM KEADAAN BAIK.

20:20

HZT2 DIPANDU FFWAN AMIRUL SYAFIQ BERSAM FFIRWANSHAH KELUAR ROUTE RUNNING TEST DI NON-PROSES AREA.

20:22

FT5 DIPANDU FF HASIF BERSAMA FF JALALUDDIN KELUAR ROUTE RUNNING TEST DI NON-PROSES AREA.

20:23

WT DIPANDU FF SHAHRUL HISHAM KELUAR ROUTE RUNNING TEST DI NON-PROSES AREA.

21:01

SEMUA KENDERAAN LAPOR SELAMAT SAMPAI DI BALAI.

21:24

EMERGENCY DRILL REPORT
TANK FIRE
DRILL NUMBER: SD/18//26
DATE: 12/04/2026
TIME: 2124HRS
LOCATION: PC INA (TANK 706)
OPC INVOLVED: PC INA
SENIOR FIRE MARSHALL: M HAFIZUDDIN
SHIFT: BRAVO SFS
CALLER: MR HASRUL (CCR PC INA)

2124 HRS: INCIDENT REPORTED BY EN. HASRUL VIA HOTLINE REGARDING A FIRE AT TANK T-706

2125 HRS: OCC ACTIVATED CEFS TEAM (SFS), MEDIC 01, AND SECURITY TEAM

2126 HRS: WIND DIRECTION RECORDED N ➝ NE AT 9KM/H

2131 HRS: CEFS TEAM AND MEDIC 03 SAFELY ARRIVED ON-SITE

2132 HRS: CEFS TEAM BEGAN SIZE-UP, CONFIRMED FIRE AT TANK T-706.

2134 HRS: FM 2 REPORTED CURRENT TANK TEMPERATURE IS AT 50°C.

2136 HRS: MARSHAL 2 REPORTED THAT THE CEFS TEAM CARRIED OUT FIRE FIGHTING OPERATIONS USING FOAM, TRANSFERRED FROM FT 5 THROUGH THE FOAM LINE SYSTEM TO TANK T 706.

2141 HRS: FM 2 REPORTED CURRENT TANK TEMPERATURE HAS BEEN REDUCE TO 30°C.

2145 HRS: MARSHAL 2 REPORTS 2 CEFS PERSONNEL AND 2 ERT MEMBERS WENT UP THE TANK TO CHECK IF THE FIRE WAS FULLY EXTINGUISHED.

2147 HRS: FM 2 REPORTED THE FIRE HAS BEEN FULLY EXTINGUISHED

2150 HRS: MARSHALL 2 REPORTED THAT OVERHAUL WAS COMPLETED AND TEMPERATURE HAD RETURNED TO NORMAL CONDITIONS.

2154 HRS: MARSHAL 2 REPORTED THE TEAM CONDUCTING THE SURVEY HAD EXITED SAFELY.

2155 HRS: MARSHAL 2 REPORTED OSC DECLARE STAND DOWN.

2206 HRS: MARSHAL 2 REPORTED ALL VEHICLES ENROUTE TO STATION

2212 HRS: ALL VEHICLES ARRIVED SAFELY SATELLITE AT FIRE STATION

22:30

MARSHAL 2 LAPOR MEMBUAT HOT WASH DRILL.

22:45

ANGGOTA BERTUGAS MEMBUAT HOUSE KEEPING PERALATAN OPERASI DI GUNAKAN SEMASA DRILL.

23:00

ANGGOTA BERTUGAS MEMBUAT PEMBERSIHAN SEMUA JENTERA OPERASI.

06:00

ANGGOTA BERTUGAS MEMBUAT HOUSE KEEPING BALAI UNTUK HAND OVER SHIFT.

08:00

RO 32045 RUSHAIRI BIN ARSHAD SERAH TUGAS MENJAGA OCC DALAM KEADAAN BAIK

Verification

Check by : Rushairi Bin Arshad Verify by : SFM M Hafizudin Zainudin