Company Logo

SATELLITE FIRE STATION OCCURRENCE REPORT v2

Shift Shift Cycle Date Emergency Drill
CHARLIE SFS Night January 1, 2026 1 0

Shift Manning

Name Vehicle
SFM Mohamad Imran Bin Jamaludin RIV3
FM Mohamad Naem Bin Sarip RIV3
Che Mohd Azmi Bin Che Loddin PM2
Nor Faiz Bin Amin FT5
Muhammad Safwan Bin Safre DP
Muhammad Azfar Bin Anuar MRV2
Muhammad Hadi Bin Hamma MRV2
Jumlad Mokhtar Bin Zol FT5
Mohamad Fakaruddin Bin Hamid WT
Mohd Azrulnizam bin Mohd Dzulkiflee ALP
Muhamad Raihan bin A Manap HZ2
Muhamad Faeiz Bin Loso -

Staff On Leave

Name Leave Type
SFM Farizuan B Deraman Annual Leave
Muhammad Amirul Bin Sulaiman Annual Leave
Muhamad Amir Alif bin Azman Annual Leave
Chrysos Eric Lipon Annual Leave

Occurrence Book Entry

Time Remarks
20:00

SAYA RO 32066 FAEIZ LOSO TERIMA TUGAS OCC DARI PASUKAN DELTA DALAM KEADAAN BAIK ADANYA.

20:04

OCC MEMBUAT UJIAN WALKIE TALKIE DAN LAPOR TUGAS ANGGOTA KEPADA RSM, CSM, USM DALAM KEADAAN BAIK ADANYA.

20:06

ANGGOTA BERTUGAS MELAKUKAN UJIAN DTRS DAN MOBILE RADIO KEPADA OCC DALAM HAL BAIK ADANYA.

20:15

ANGGOTA BERTUGAS MELAKUKAN PEMERIKSAAN JENTERA OPERASI, PERALATAN BERMOTOR DAN TIDAK BERMOTOR DALAM HAL BAIK ADANYA.

20:25

FORD DIPANDU FF JUMLAD LAPOR KELUAR GATE 3, TUGAS-TUGAS KHAS.

20:26

FT5 DI PANDU FF FAIZ LAPOR KELUAR MEMBUAT ROAD RUNNING DI NONPROSES AREA DALAM KEADAAN BAIK.

20:28

DP DIPANDU FF SAFWAN LAPOR KELUAR MEMBUAT ROAD RUNNING DI NONPROSES AREA DALAM KEADAAN BAIK.

21:12

EMERGENCY REPORT
SPECIAL ASSISTANCE (BEEHIVE)
EMERGENCY NUMBER: SE/01/2026
DATE: 01/01/2026
TIME: 2112HRS
LOCATION: ETP
OPC INVOLVED: PRPC UF
MARSHALL: MR NAEM SARIP
SHIFT: CHARLIE SFS
CALLER: MR SAZALI (USM)

2112HRS: OCC RECIVED CALL FROM MR SAZALI (USM) INFORMED THERE HAVE BEEHIVE AT AREA ETP

2112HRS: OCC ACTIVATED CEFS TEAM TO THE LOCATION.

2113HRS: FM 2 REPORTED 3 CEFS PERSONNEL WITH EMERGENCY VEHICLES (MRV 2) TO LOCATION.

2120HRS: FM 2 REPORTED CEFS TEAM ARRIVED AT AREA ETP AND CONFIRMED THAT BEE LOCATED AT THE 10 FEET HIGH SIZE WAS DIAMETER 0.5 METER AND BEGIN SIZE UP.

2122HRS: FM 2 REPORTED SETUP 2 RESPONDER COMPLETED WITH BEE SUIT AND 2 BAYGON SPRAY WERE READY ON THE TOP TO DEMOLISHED THE HIVE.

2126HRS: FM 2 REPORTED A BEEHIVE WAS SUCCESSFULLY DEMOLISH AND THE AREA WAS SAFE FROM ANY BEE THREAT.

2127HRS: FM 2 REPORTED OVERHAUL ACTIVITY WAS CONDUCTED.

2128HRS: FM 2 DECLARED OPERATION STAND DOWN AND CEFS TEAM WITH EMERGENCY VEHICLES BACK TO FIRE STATION.

2130HRS: FM 2 REPORTED CEFS TEAM SAFELY ARRIVED AT SATELLITE FIRE STATION.

21:31

KESMUA JENTERA LAPOR SELAMAT SAMPAI DI BALAI DALAM KEADAAN BAIK DAN TERKAWAL.

22:00

SEMUA ANGGOTA BERKUMPUL DI BILIK ECC UNTUK MEMBUAT AKTIVITI KELAS TEORI DAN PRAKTIKAL.

06:00

SEMUA ANGGOTA BERTUGAS MELAKUKAN HOUSE KEEPING BALAI DAN JENTERA SEBELUM AKTIVITI SERAH TUGAS DALAM KEADAAN BAIK.

08:00

OCC 32066 FAEIZ LOSO SERAH TUGAS BILIK KAWALAN KEPADA PASUKAN ALPHA DALAM KEADAAN BAIK.

Verification

Check by : Muhamad Faeiz Bin Loso Verify by : SFM Mohamad Imran Bin Jamaludin
Faeizloso